Compactor - Garbage or Cardboard
![]() |
General Compactor garbage service should be used when one location is expected to generate more than 45 cubic yards of garbage per week. These units may be the best alternative for locations that are extremely tight for space and where buildings are clustered so that access to the compactor is relatively close. Custodians are mainly responsible for removing garbage from the buildings on campus, but occasionally faculty, staff, or students will want to use it. A cardboard dumpster will still need to be placed next to the compactor unit. |
|
![]() |
Specifications |
![]() |
|
Size of Unit |
Total Length |
Width |
Height |
|
15 cubic yard |
16’5" |
9’ |
8’5" |
|
20 cubic yard |
18’11" |
9’ |
8’5" |
|
25 cubic yard |
20’11" |
9’ |
9’8" |
|
30 cubic yard |
22’5" |
9’ |
9’8" |
|
plus 2 feet of clearance around container |
|||
|
Concrete Pad Requirements: |
Pad to be 10 ft. wide with a length of 5 ft. greater than the length of the compactor. Concrete to be minimum 3000 psi, steel reinforced, 6" thick. |
|
Electrical Requirements: |
Electrical Motor |
3/60/230-460 |
|
Electrical Control Voltage |
120 VAC |
PSSI purchases and maintains all dumpsters and compactors on campus. Specifications subject to change. To determine
the level of service needed for new projects or for more information, please contact Julie Muir at PSSI at (650) 321-4236 or